📚 Part of: Ancient Indian Agriculture & Bollywood Mcqs: Historical Crops & Film Industry

A and B can do a piece of work in 12 days and 24 days respectively. If they work at it together for 4 days after which A leaves. In how many days will B complete rest of the work?

Category: Miscellaneous Indian Gk

Correct Answer: A) 12 days.

Exam Relevance: CAT, MAT, Bank PO, SSC CGL

Difficulty: Moderate

Concept notes:

In work and time problems, the efficiency of individuals is often calculated as the fraction of work they can complete in a day. When working together, their efficiencies are added. After a certain period, if one person leaves, the remaining work is completed by the other at their individual rate.

Common Mistakes:
  • Misunderstanding the combined work rate.
  • Incorrectly calculating the remaining work after A leaves.
  • Confusing the time taken by B to complete the remaining work with the total time.
Explanation:

To solve this problem, we need to understand the concept of work and time, specifically how to calculate the combined work rate and the remaining work after a certain period.

First, let's determine the individual work rates of A and B. A can complete the work in 12 days, so A's work rate is \( \frac{1}{12} \) of the work per day. Similarly, B can complete the work in 24 days, so B's work rate is \( \frac{1}{24} \) of the work per day.

When A and B work together, their combined work rate is the sum of their individual work rates:

\[ \text{Combined work rate} = \frac{1}{12} + \frac{1}{24} = \frac{2}{24} + \frac{1}{24} = \frac{3}{24} = \frac{1}{8} \]

This means that together, A and B can complete \( \frac{1}{8} \) of the work per day.

Next, we calculate the amount of work completed by A and B together in 4 days:

\[ \text{Work completed in 4 days} = 4 \times \frac{1}{8} = \frac{4}{8} = \frac{1}{2} \]

So, after 4 days, half of the work is completed, and the remaining work is:

\[ \text{Remaining work} = 1 - \frac{1}{2} = \frac{1}{2} \]

Now, B will complete the remaining \( \frac{1}{2} \) of the work alone. Since B's work rate is \( \frac{1}{24} \) of the work per day, the time B needs to complete the remaining work is:

\[ \text{Time for B to complete remaining work} = \frac{\frac{1}{2}}{\frac{1}{24}} = \frac{1}{2} \times 24 = 12 \text{ days} \]

Therefore, the correct answer is that B will complete the remaining work in 12 days. This matches option A.

In summary, the key steps are:

1. Calculate the individual work rates of A and B.

2. Determine the combined work rate of A and B.

3. Calculate the work completed by A and B together in 4 days.

4. Find the remaining work after 4 days.

5. Calculate the time B needs to complete the remaining work alone.

This problem tests the understanding of work and time concepts, including combined work rates and the calculation of remaining work.

Option Analysis:
  • Option A: This option is correct. After A and B work together for 4 days, the remaining work is completed by B alone in 12 days. This is calculated by first determining the combined work rate of A and B, then finding the fraction of work completed in 4 days, and finally calculating the time B needs to complete the remaining work.
  • Option B: This option is incorrect. It suggests that B would complete the remaining work in 6 days, which is not correct based on the combined work rate and the remaining work after 4 days of A and B working together.
  • Option C: This option is incorrect. It suggests that B would complete the remaining work in 8 days, which is not correct based on the combined work rate and the remaining work after 4 days of A and B working together.
  • Option D: This option is incorrect. "CNBD" is not a valid option for this problem and does not provide a meaningful answer to the question.

Mnemonic: A + B = Together, A leaves = B alone

⬅️ Back to Ancient Indian Agriculture & Bollywood Mcqs: Historical Crops & Film Industry – Practice all questions