Part of: Miscellaneous Indian Gk set 357

A and B can do a piece of work in 12 days and 24 days respectively. If they work at it together for 4 days after which A leaves. In how many days will B complete rest of the work?

Category: Miscellaneous Indian Gk

Hint: Calculate the work done by A and B together in 4 days and then find out how much work is left for B

Correct Answer: A) 12 days.

Exam Relevance: CAT, MAT, Bank PO, SSC

Difficulty: Moderate

Explanations:

In work and time problems, the work rate of each individual is calculated as the reciprocal of the time they take to complete the work alone. For example, if A can complete a piece of work in 12 days, A's work rate is 1/12 of the work per day. Similarly, if B can complete the same piece of work in 24 days, B's work rate is 1/24 of the work per day.

When A and B work together, their combined work rate is the sum of their individual work rates. Therefore, the combined work rate of A and B is:

\[ \text{Combined work rate} = \frac{1}{12} + \frac{1}{24} = \frac{2}{24} + \frac{1}{24} = \frac{3}{24} = \frac{1}{8} \]

This means that together, A and B can complete 1/8 of the work per day. If they work together for 4 days, the amount of work they complete is:

\[ \text{Work done in 4 days} = 4 \times \frac{1}{8} = \frac{4}{8} = \frac{1}{2} \]

So, A and B together complete half of the work in 4 days. The remaining work is:

\[ \text{Remaining work} = 1 - \frac{1}{2} = \frac{1}{2} \]

After A leaves, B continues to work alone. B's work rate is 1/24 of the work per day. To find out how many days B will take to complete the remaining half of the work, we use the formula:

\[ \text{Time taken by B} = \frac{\text{Remaining work}}{\text{B's work rate}} = \frac{\frac{1}{2}}{\frac{1}{24}} = \frac{1}{2} \times 24 = 12 \text{ days} \]

Therefore, B will take 12 days to complete the remaining half of the work alone. This confirms that the correct answer is 12 days.

Option Analysis:
  • Option A: This option is correct. A and B together complete 1/12 + 1/24 = 1/8 of the work per day. In 4 days, they complete 4 × 1/8 = 1/2 of the work. The remaining work is 1/2, and B alone completes 1/24 of the work per day, so B will take 12 days to complete the remaining work.
  • Option B: This option is incorrect. B alone cannot complete the remaining half of the work in 6 days because B's work rate is 1/24 per day, which means B would need 12 days to complete half the work.
  • Option C: This option is incorrect. B alone cannot complete the remaining half of the work in 8 days because B's work rate is 1/24 per day, which means B would need 12 days to complete half the work.
  • Option D: This option is incorrect. "CNBD" is not a valid answer choice for this problem. The correct answer is 12 days, as calculated.

Mnemonic: Work Done = Rate × Time

Back to Miscellaneous Indian Gk set 357 – Practice all questions