📚 Part of: Indian Agriculture And Constitutional Law Mcq Quiz

A can do a piece of work in 30 days. He works at it for 10 days and leaves. B finishes the remaining work in 16 days. In how many days can they together do the work?

Category: Miscellaneous Indian Gk

Correct Answer: B) 13 1/3 days.

Exam Relevance: CAT, GMAT, GRE, Bank PO, SSC CGL

Difficulty: Moderate

Concept notes:

In work and time problems, the efficiency of individuals is often calculated as the fraction of work done per day. The combined efficiency of multiple workers is the sum of their individual efficiencies. The total time taken to complete the work is the reciprocal of the combined efficiency.

Common Mistakes:
  • Students often confuse the total work done with the work done per day.
  • They may incorrectly assume that the time taken by A and B together is the average of the times taken by A and B individually.
  • Students might forget to convert the combined efficiency back into days to find the total time taken.
Explanation:

To solve this problem, we need to determine the work rates of A and B and then find the combined work rate to determine how long it would take for them to complete the work together.

First, let's calculate the work rate of A. Since A can complete the work in 30 days, A's work rate is:

\[ \text{Work rate of A} = \frac{1}{30} \text{ of the work per day} \]

A works for 10 days, so the amount of work A completes is:

\[ \text{Work done by A in 10 days} = 10 \times \frac{1}{30} = \frac{10}{30} = \frac{1}{3} \]

This means that \(\frac{2}{3}\) of the work remains after A leaves. B completes the remaining \(\frac{2}{3}\) of the work in 16 days. Therefore, B's work rate is:

\[ \text{Work rate of B} = \frac{\frac{2}{3}}{16} = \frac{2}{3 \times 16} = \frac{2}{48} = \frac{1}{24} \text{ of the work per day} \]

Now, we need to find the combined work rate of A and B. The combined work rate is the sum of their individual work rates:

\[ \text{Combined work rate} = \frac{1}{30} + \frac{1}{24} \]

To add these fractions, we need a common denominator. The least common multiple of 30 and 24 is 120. So, we convert the fractions:

\[ \frac{1}{30} = \frac{4}{120} \]

\[ \frac{1}{24} = \frac{5}{120} \]

Adding these fractions gives:

\[ \text{Combined work rate} = \frac{4}{120} + \frac{5}{120} = \frac{9}{120} = \frac{3}{40} \]

The combined work rate of A and B is \(\frac{3}{40}\) of the work per day. To find the total time taken to complete the work together, we take the reciprocal of the combined work rate:

\[ \text{Total time} = \frac{1}{\frac{3}{40}} = \frac{40}{3} = 13 \frac{1}{3} \text{ days} \]

Therefore, A and B together can complete the work in 13 \(\frac{1}{3}\) days, which is the correct answer.

Option Analysis:
  • Option A: This option is incorrect. The calculation of the combined work rate and the time taken to complete the work does not result in 12 days. The correct time is longer than 12 days.
  • Option B: This option is correct. The combined work rate of A and B results in a total time of 13 1/3 days to complete the work together.
  • Option C: This option is incorrect. The calculation of the combined work rate and the time taken to complete the work does not result in 16 2/3 days. The correct time is shorter than 16 2/3 days.
  • Option D: This option is incorrect. The calculation of the combined work rate and the time taken to complete the work does not result in 18 days. The correct time is shorter than 18 days.

Mnemonic: Work and Time: "A + B = Total Work Done"

⬅️ Back to Indian Agriculture And Constitutional Law Mcq Quiz – Practice all questions