Part of: Miscellaneous Indian Gk set 344

A can do a piece of work in 30 days. He works at it for 10 days and leaves. B finishes the remaining work in 16 days. In how many days can they together do the work?

Category: Miscellaneous Indian Gk

Hint: Calculate the fraction of work done by A and B separately, then find their combined rate.

Correct Answer: B) 13 1/3 days.

Exam Relevance: CAT, MAT, Bank PO, SSC CGL

Difficulty: Moderate

Explanations:

In work and time problems, the work rate of an individual is the fraction of the work they can complete in one day. The combined work rate of multiple individuals is the sum of their individual work rates. The total time taken to complete the work together is the reciprocal of the combined work rate.

Let's break down the problem step-by-step:

1. **Determine the work rate of A:** - A can complete the work in 30 days. - Therefore, A's work rate is \( \frac{1}{30} \) of the work per day. 2. **Calculate the work done by A in 10 days:** - In 10 days, A completes \( 10 \times \frac{1}{30} = \frac{10}{30} = \frac{1}{3} \) of the work. 3. **Determine the remaining work:** - The remaining work is \( 1 - \frac{1}{3} = \frac{2}{3} \) of the work. 4. **Determine the work rate of B:** - B completes the remaining \( \frac{2}{3} \) of the work in 16 days. - Therefore, B's work rate is \( \frac{\frac{2}{3}}{16} = \frac{2}{3 \times 16} = \frac{2}{48} = \frac{1}{24} \) of the work per day. 5. **Calculate the combined work rate of A and B:** - The combined work rate is \( \frac{1}{30} + \frac{1}{24} \). - To add these fractions, find a common denominator, which is 120. - \( \frac{1}{30} = \frac{4}{120} \) and \( \frac{1}{24} = \frac{5}{120} \). - Therefore, the combined work rate is \( \frac{4}{120} + \frac{5}{120} = \frac{9}{120} = \frac{3}{40} \) of the work per day. 6. **Determine the total time taken to complete the work together:** - The total time taken is the reciprocal of the combined work rate. - \( \frac{1}{\frac{3}{40}} = \frac{40}{3} = 13 \frac{1}{3} \) days.

Thus, A and B together can complete the work in \( 13 \frac{1}{3} \) days, which corresponds to option B.

Option Analysis:
  • Option A: Incorrect. This option does not account for the correct combined work rate of A and B. The calculation of the combined work rate and the reciprocal of that rate does not yield 12 days.
  • Option B: Correct. This option correctly calculates the combined work rate of A and B and finds the reciprocal of that rate to determine the total time taken to complete the work together.
  • Option C: Incorrect. This option overestimates the time taken by A and B to complete the work together. The correct combined work rate and its reciprocal do not yield 16 2/3 days.
  • Option D: Incorrect. This option underestimates the combined work rate of A and B, leading to an incorrect total time of 18 days to complete the work together.

Mnemonic: Work done = Rate × Time

Back to Miscellaneous Indian Gk set 344 – Practice all questions